Commissioning checklist
The tests that should happen before the container is unpacked and forgotten.
Structure
Column plumb, gutter level over the full length, bay square, roof line and vent clearances. Photograph each check with a reference.
Covering
Glass or film tension, sealant lines, gutter flow with a water test, and leaks at the wall junctions.
Systems
Fan and pump rotation, flow rates against design, cooling temperature drop, heating ramp, screen travel and limit switches, irrigation uniformity per zone.
Control
Set points, day/night ramps, alarm list, remote access and a logged 24-hour run with the crop strategy loaded.